Activity resource estimating, activity duration estimating, and cost estimating cannot occur at the same time on projects.
Correct Answer:
Verified
Q24: Resource loading defines the amount of time
Q25: In CPM, ES, EF, LS, and LF
Q26: Resource loading is the process of rescheduling
Q27: The three types of estimates in three-point
Q28: CPM produces three key pieces of information.
Q30: In CPM, you calculate task time by
Q31: Crashing a project often adds or removes
Q32: If a task has free slack it
Q33: PERT uses a weighted average approach, or
Q34: The critical path is a path through