In this tool for estimating percentage complete, when a task or work package is started, it is immediately assigned a 50 percent complete status until it is completed and then is set to 100 percent complete.
A) 0-100 percent rule
B) 50-50 percent rule
C) Interval percent rule
D) EVM
Correct Answer:
Verified
Q69: The cost _ process is concerned with
Q70: A key tool used as input for
Q71: In the _ management knowledge area, the
Q72: In this tool for estimating percentage complete,
Q73: In the time management knowledge area, the
Q75: The cost management _ area is responsible
Q76: This is equal to the actual costs
Q77: The schedule _ process is concerned with
Q78: This equals the ratio of EV to
Q79: With this method of percentage complete estimation,