Question 61
Multiple Choice
Use of the shortest processing time sequencing rule generally results in
Question 62
Multiple Choice
Flow time represents the time
Question 63
Multiple Choice
Which of the following dispatching rules is typically the best technique for taking first those jobs with the most urgent needs?
Question 64
Multiple Choice
A recent advance in short-term scheduling that makes use of expert systems and simulation in solving dynamic scheduling problems is
Question 65
Multiple Choice
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's rule, what is the optimum sequence of jobs and the minimum time for completion of all jobs?
Job
Alpha
Beta
R
20
10
S
25
35
T
50
20
U
15
35
V
55
75
\begin{array} { | c | c | c | } \hline \text { Job } & \text { Alpha } & \text { Beta } \\\hline R & 20 & 10 \\\hline \mathrm { S } & 25 & 35 \\\hline \mathrm { T } & 50 & 20 \\\hline \mathrm { U } & 15 & 35 \\\hline \mathrm { V } & 55 & 75 \\\hline\end{array}
Job
R
S
T
U
V
Alpha
20
25
50
15
55
Beta
10
35
20
35
75
Question 66
Multiple Choice
Which of the following are limitations of rules-based dispatching systems?
Question 67
Multiple Choice
Five jobs are waiting to be processed. Their processing times and due dates are given below. Using the earliest due date dispatching rule, in which order should the jobs be processed?
Job
Processing
Time (days)
Job due date
(days)
A
4
7
B
2
4
C
8
11
D
3
5
E
5
8
\begin{array} { | c | c | c | } \hline \text { Job } & \begin{array} { c } \text { Processing } \\\text { Time (days) }\end{array} & \begin{array} { c } \text { Job due date } \\\text { (days) }\end{array} \\\hline \text { A } & 4 & 7 \\\hline \text { B } & 2 & 4 \\\hline \text { C } & 8 & 11 \\\hline \text { D } & 3 & 5 \\\hline \text { E } & 5 & 8 \\\hline\end{array}
Job
A
B
C
D
E
Processing
Time (days)
4
2
8
3
5
Job due date
(days)
7
4
11
5
8
Question 68
Multiple Choice
Eight jobs have been sequenced at a single work center. Total processing time for the eight jobs is 34 hours and total flow time for the sequence is 85 hours. For this schedule, utilization is __________ and average jobs in the system is __________.
Question 69
Multiple Choice
Which of the following is an advantage of the FCFS dispatching rule when used in services?
Question 70
Multiple Choice
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Sigma before work center Delta. According to Johnson's rule, what sequence of jobs will minimize the completion time for all jobs?
Job
Sigma
Delta
R
40
10
S
25
30
T
50
20
U
35
35
V
55
15
\begin{array} { | c | c | c | } \hline \text { Job } & \text { Sigma } & \text { Delta } \\\hline R & 40 & 10 \\\hline \mathrm { S } & 25 & 30 \\\hline \mathrm { T } & 50 & 20 \\\hline \mathrm { U } & 35 & 35 \\\hline \mathrm { V } & 55 & 15 \\\hline\end{array}
Job
R
S
T
U
V
Sigma
40
25
50
35
55
Delta
10
30
20
35
15
Question 71
Multiple Choice
The priority rule that sequences jobs using the smallest ratio of due date from today to processing time is
Question 72
Multiple Choice
Sequencing (or dispatching)
Question 73
Multiple Choice
Average completion time for a schedule sequence at a work center is the ratio of
Question 74
Multiple Choice
Which critical ratio value implies that a job is already late?
Question 75
Multiple Choice
The most appropriate sequencing rule to use if the goal is to dynamically track the progress of jobs and establish relative priority on a common basis is
Question 76
Multiple Choice
Five jobs are waiting for processing through two work centers. Their processing time (in minutes) at each work center is contained in the table below. Each job requires work center Alpha before work center Beta. According to Johnson's rule, which job should be scheduled first in the sequence?
Job
Alpha
Beta
R
20
10
S
25
35
T
50
20
U
15
35
V
55
75
\begin{array} { | c | c | c | } \hline \text { Job } & \text { Alpha } & \text { Beta } \\\hline R & 20 & 10 \\\hline \mathrm { S } & 25 & 35 \\\hline \mathrm { T } & 50 & 20 \\\hline \mathrm { U } & 15 & 35 \\\hline \mathrm { V } & 55 & 75 \\\hline\end{array}
Job
R
S
T
U
V
Alpha
20
25
50
15
55
Beta
10
35
20
35
75
Question 77
Multiple Choice
Which of the following dispatching rules tends to minimize job flow time?
Question 78
Multiple Choice
When a set of jobs must pass through two workstations whose sequence is fixed, __________ is the sequencing rule most commonly applied.
Question 79
Multiple Choice
Conventional MRP uses time buckets that do not recognize capacity limits, and in fact ignores capacity issues. A more realistic scheduling system that includes work center capacities and other resource availabilities is