On 1 January 2014, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows:
Estimated costs were $50 000 000. The project was 35 per cent complete at the end of 2014, 75 per cent complete at the end of 2015 and 100 per cent complete at the end of 2016. Revenues and costs were as estimated. How much profit was earned during 2016 if the percentage of completion method was used?
A) $3 500 000
B) $5 600 000
C) $6 343 750
D) $14 000 000
Correct Answer:
Verified
Q12: At what point would you expect revenue
Q23: Junction Company had the following transactions,among others,during
Q29: On 1 January 2014, Peter Ltd signed
Q31: Opec Ltd manufactures crystal balls. Transactions for
Q31: At what point would you expect revenue
Q32: The profit for a particular project of
Q34: Holidays Ltd manufactures caravans. Transactions for the
Q35: The percentage of completion profit for a
Q36: Toy Company manufactures toy koalas. Transactions for
Q37: On 1 January 2014, Peter Ltd signed
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents