On 1 January 2014, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows:
Estimated costs were $50 000 000. The project was 35 per cent complete at the end of 2014, 75 per cent complete at the end of 2015 and 100 per cent complete at the end of 2016. Revenues and costs were as estimated. How much profit was earned during 2014 if the percentage of completion method was used?
A) $3 281 250
B) $4 200 000
C) $4 900 000
D) $5 600 000
Correct Answer:
Verified
Q12: At what point would you expect revenue
Q24: On 1 January 2015, Romulus Ltd signed
Q25: On 1 January 2015, Romulus Ltd signed
Q27: Holidays Ltd manufactures caravans. Transactions for the
Q31: At what point would you expect revenue
Q31: Opec Ltd manufactures crystal balls. Transactions for
Q33: On 1 January 2014, Peter Ltd signed
Q34: Holidays Ltd manufactures caravans. Transactions for the
Q35: The percentage of completion profit for a
Q37: The percentage of completion profit for a
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents