On 1 January 2014, Peter Ltd signed a contract worth $64 000 000 to construct the Cycling Stadium. The stadium was to be built over three years, with progress payments as follows:
Estimated costs were $50 000 000. The project was 35 per cent complete at the end of 2014, 75 per cent complete at the end of 2015 and 100 per cent complete at the end of 2016. Revenues and costs were as estimated. How much profit was earned during 2015 if the percentage of completion method was used?
A) $5 600 000
B) $4 375 000
C) $3 500 000
D) $10 500 000
Correct Answer:
Verified
Q12: At what point would you expect revenue
Q23: Junction Company had the following transactions,among others,during
Q32: The profit for a particular project of
Q33: On 1 January 2014, Peter Ltd signed
Q33: The profit for a particular project of
Q34: Holidays Ltd manufactures caravans. Transactions for the
Q36: Toy Company manufactures toy koalas. Transactions for
Q36: The percentage of completion profit for a
Q43: Leslie Ltd has found an error in
Q48: Leslie Ltd has found an error in
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents