Table 3.13
You are responsible for managing a project with the following activities (times are given in weeks) .
 Activity  Expected  Time  Immediate  Predecessor (s) A8 B 10 C 7 A,B  D 5 B  E 12 C  F 7 C,D  G 6 E,F  H 10 F \begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Expected } \\\text { Time }\end{array} & \begin{array} { c } \text { Immediate } \\\text { Predecessor } ( \mathrm { s } ) \end{array} \\\hline \mathbf { A } & 8 & \cdots - \\\text { B } & 10 & - \\\text { C } & 7 & \text { A,B } \\\text { D } & 5 & \text { B } \\\text { E } & 12 & \text { C } \\\text { F } & 7 & \text { C,D } \\\text { G } & 6 & \text { E,F } \\\text { H } & 10 & \text { F } \\\hline\end{array}
-Using Table 3.13,if the expected time for activity E is decreased to 8 weeks,what is the new expected completion time for the project?


A) 31 weeks or less
B) 32-33 weeks
C) 34-35 weeks
D) more than 35 weeks

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents