Table 3.12
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 3.12,which of the following activities has the largest amount of slack?
A) Activity C
B) Activity D
C) Activity E
D) Activity H
Correct Answer:
Verified