Table 3.10
You are responsible for managing a project with the following activities
(times are given in weeks) .
-Using Table 3.10,if the expected time for activity B is changed to 18 weeks,by how many weeks will the project's expected completion time increase?
A) It will not change.
B) It will increase by 1 or 2 weeks.
C) It will increase by 3 or 4 weeks.
D) It will increase by more than 4 weeks.
Correct Answer:
Verified
Q20: The _ is a statement of all
Q39: A(n) _ determines the sequence for undertaking
Q104: Table 3.10
You are responsible for managing
Q105: Assuming a beta distribution is being used,if
Q107: Table 3.11
You are responsible for managing
Q108: Assuming a beta distribution is being used,if
Q111: Table 3.10
You are responsible for managing
Q112: Table 3.13
You are responsible for managing
Q113: Table 3.10
You are responsible for managing
Q128: If the sum of the variances on
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents