A bottleneck is:
A) A resource that has the maximum capacity in the facility
B) A resource whose capacity is less than the capacity of all other resources and whose capacity is less than the demand placed on it
C) A resource that should not be blocked or starved
D) A resource that has the fastest processing time
E) Two of the above
Correct Answer:
Verified
Q3: Which of the following statements is incorrect
Q4: Which of the following statements is NOT
Q4: The theory of constraints (TOC)is:
A)A strategic technique
Q6: Theory of constraints,as it applies to business
Q7: Lead time for completion of a job
Q8: The overriding problem in batch scheduling is:
A)Regulating
Q8: Which of the following is NOT primarily
Q11: In the language of constraint management,inventory is:
A)The
Q17: Use a Gantt chart to schedule the
Q25: Throughput is defined as the difference between
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents