Question 61
Multiple Choice
Completion time (from start to finish) of a building remodeling project is normally distributed with a mean of 200 work-days and a standard deviation of 10 work-days.To be 99% sure that we will not be late in completing the project,we should request a completion time of _______ work-days.
Question 62
Multiple Choice
At a certain workstation in an assembly line,the time required to assemble a component is exponentially distributed with a mean time of 10 minutes.Find the probability that a component is assembled in 7 minutes or less?