Services
Discover
Homeschooling
Ask a Question
Log in
Sign up
Filters
Done
Question type:
Essay
Multiple Choice
Short Answer
True False
Matching
Topic
Statistics
Study Set
Operations and Supply Management
Quiz 3: Project Management
Path 4
Access For Free
Share
All types
Filters
Study Flashcards
Practice Exam
Learn
Question 21
True/False
One of the assumptions of CPM is that project activity times can be estimated accurately.
Question 22
True/False
The "Z" value used to calculate the probabilities in CPM analysis is based on the Beta probability distribution.
Question 23
True/False
The expected time estimate in a CPM three time estimate procedure is a weighted average formula.
Question 24
True/False
Slack activity time is the difference between the early start and the late finish of a project activity time.
Question 25
True/False
In the Time-Cost CPM model,cost is a linear function of time.
Question 26
True/False
In a CPM analysis if you subtract the late finish from the early finish the result is the activity's slack time.
Question 27
True/False
When reducing the planned duration of a project using the Time-Cost CPM model we select the activity to crash by determining the cost of each alternative and selecting the one whose cost is the greatest.
Question 28
True/False
One of the assumptions made using CPM is that project activities can be identified with clear beginning and ending points.
Question 29
True/False
The critical path in a CPM analysis is found by locating the activities times with zero slack.
Question 30
True/False
To calculate the variances of activity times in CPM analysis we must use all three time estimates (i.e. ,optimistic,most likely and pessimistic time estimates).
Question 31
True/False
Calculating the early start and early finish times for each activity in a CPM analysis does not provide any useful information.
Question 32
True/False
The activity direct costs associated with a project might include giving workers overtime to complete a project in less-than the expected time.
Question 33
True/False
When the time estimates in a CPM analysis vary into optimistic,most likely and pessimistic,we should use the single time estimate CPM procedure.
Question 34
True/False
In calculating the probabilities in a CPM analysis the desired time is determined by calculating the expected time for the project as a whole.
Question 35
True/False
You are managing a project and need to cut the cost of the project.You decide to transfer workers to another job to cut the project's costs.Costs associated with transferring the workers are an example of project indirect costs.