You have collected the data for a time-cost CPM scheduling model analysis.The time is in days and the project "direct costs" are given here. The indirect costs for the project are determined on a daily duration basis.If the project lasts 16 days, the total indirect costs are $400; 15 days, they will be $250; 14 days, they will be $200; and 13 days, they will be $100.If you crash this project by one day what is the total (i.e., direct and indirect) project cost? ____________________
E.A costs $100/day to crash, D costs $150/day to crash, and E costs $400/day to crash.Reducing the duration of A by one day at an additional cost of $100 is the most economical.Direct costs are now $400 + $100 + $200 + $400 + $500 + $200 + $100 = $1,900.Overall duration of the project is 15 days, and indirect costs are $250.The total cost of crashing this project for one day is $2,150.
Correct Answer:
Verified
Explanation: The critical path is...
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q63: You have collected the data for a
Q63: In CPM analysis, it is generally expected
Q64: You have the following time and cost
Q65: Here are the data for a time-cost
Q66: What do the initials EVM stand for?
Q67: You have just performed a CPM analysis
Q70: Popular project management software used in mid-sized
Q70: What are "project milestones?" _
Q71: Here are the data for a time-cost
Q72: Here are the data for a time-cost
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents