Here are the data for a time-cost CPM scheduling model analysis.The time is in days and the costs include both direct and indirect costs. What are the total time of this project and total normal cost?
A) Total time is 13 days, total cost is $1,200.
B) Total time is 12 days, total cost is $1,700.
C) Total time is 11 days, total cost is $1,600.
D) Total time is 10 days, total cost is $1,750.
E) Total time is 9 days, total cost is $1,700.
Correct Answer:
Verified
Q45: An advantage of a pure project where
Q61: What is the most basic requirement of
Q63: You have collected the data for a
Q63: In CPM analysis, it is generally expected
Q64: You have the following time and cost
Q66: What do the initials EVM stand for?
Q67: You have collected the data for a
Q67: You have just performed a CPM analysis
Q70: Popular project management software used in mid-sized
Q70: What are "project milestones?" _
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents