While the manage communications process is underway,effective information distribution often requires the project manager and team to accomplish all of the following activities EXCEPT:
A) determine any information needs not already uncovered
B) collect information on executed work and work in progress
C) develop responses to identifies risks
D) report progress to all stakeholders
Correct Answer:
Verified
Q24: Which of the following measures is best
Q25: This is the process of reviewing all
Q26: Q27: Which of these is NOT one of Q28: Q30: Q31: All of the following accurately apply to Q32: With respect to performance reporting,which of these Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents