Question 25

Multiple Choice

This is the process of reviewing all change proposals,estimating their impact on project goals wherever appropriate,approving or declining changes,and managing changes to deliverables,schedules,budgets and the project management plan: ​ 


A)  Perform project monitoring. 
B)  Perform variance analysis and control. 
C)  Perform integrated change control. 
D)  Perform configuration management

Correct Answer:

verifed

Verified