Multiple Choice
Figure 8-4 Project Crashing Information
-Consider the project crashing information presented in Figure 8-4.What is the incremental cost to achieve a one-day reduction in the duration of this project in the most cost efficient manner?
A) $ 30
B) $ 35
C) $ 40
D) $ 60
Correct Answer:
Verified