Project managers must often face the challenge of compressing the project schedule.All of the following actions can be taken to reduce the duration of the critical path EXCEPT:
A) Reduce the project scope and /or quality.
B) Overlap sequential activities using finish-to-finish, start-to-start, or start-to-finish relationships.
C) Use the float in critical path activities
D) Partially overlap sequential activities by using time leads.
Correct Answer:
Verified