If a project is expected to be completed in 68 days with a project variance of 9 days,what is the probability that the project will be completed within 50 days?
A) 0%
B) between 5% and 10%
C) between 15% and 30%
D) over 35%
Correct Answer:
Verified
Q42: If a project is expected to be
Q43: In considering crashing activities,we first want to
Q44: A project's variance is _.
A)the sum of
Q45: If a project has an expected completion
Q46: If a project is expected to be
Q48: If a project is expected to be
Q49: If a project has an expected completion
Q50: The probability that a project will be
Q51: If a project has an expected completion
Q52: The normal activity duration of Activity X