If a project is expected to be completed in 68 days with a project variance of 21 days,what is the probability that the project will be completed within 90 days?
A) between 5% and 10%
B) between 15% and 20%
C) between 25% and 30%
D) none of these
Correct Answer:
Verified
Q37: Which of the following statements is true
Q38: The work breakdown structure _.
A)identifies the individual
Q39: In calculating the probability of a project
Q40: The project's baseline _.
A)is the standard against
Q41: If a project has an expected completion
Q43: In considering crashing activities,we first want to
Q44: A project's variance is _.
A)the sum of
Q45: If a project has an expected completion
Q46: If a project is expected to be
Q47: If a project is expected to be