Question 81
Multiple Choice
A
disadvantage
of product-oriented layout is that
Question 82
Multiple Choice
A production line is to be designed for a product whose completion requires 21 minutes of work. The factory works 400 minutes per day. Can an assembly line with five workstations make 100 units per day?
Question 83
Multiple Choice
Which of the following is a common heuristic for assembly line balancing?
Question 84
Multiple Choice
In assembly line balancing, the theoretical minimum number of workstations is
Question 85
Multiple Choice
The central problem in product-oriented layout planning is
Question 86
Multiple Choice
A production line is to be designed for a job with four tasks. The task times are 2.4 minutes, 1.4 minutes, 0.9 minutes, and 1.7 minutes. After line balancing, the largest possible assigned cycle time is ________ and the smallest possible assigned cycle time is ________ minutes.
Question 87
Multiple Choice
Which of these layouts is most suitable for processing sugar from sugar beets or sugar cane?
Question 88
Multiple Choice
An assembly line consists of 21 tasks grouped into 5 workstations. The sum of the 21 task times is 85 minutes. The largest assigned cycle time is 20 minutes. The efficiency of this line is
Question 89
Multiple Choice
The main advantage of a product-oriented layout is typically
Question 90
Multiple Choice
Daily capacity of a product layout is determined by
Question 91
Multiple Choice
Cycle time is computed as
Question 92
Multiple Choice
A production line is to be designed to make 500 El-More dolls per day. Each doll requires 11 activities totaling 16 minutes of work. The factory operates 750 minutes per day. The required cycle time for this assembly line is