A PERT (Program Evaluation and Review Technique) Chart Is Used

Question 14

Multiple Choice

A PERT (Program Evaluation and Review Technique) chart is used to:


A) Diagram the flow and timing of all activities related to a project
B) Evaluate employee strengths and weaknesses during performance reviews
C) Outline responsibilities of staff supervisors
D) Keep track of vendor compliance with delivery schedules

Correct Answer:

verifed

Verified