If a change affects the schedule
A) the Owner and Architect will know
B) the Contract Administrator should document and notify the Architect and Owner
C) pricing of the change should be submitted immediately
D) a solution must first be found before notifying all concerned
Correct Answer:
Verified
Q1: Fortunately, Constructive Acceleration guarantees the Contractor will
Q2: In most cases, the Contract Administrator has
Q3: Without a change order clause in the
Q4: In most cases, a flaw or ambiguity
Q5: Until one knows otherwise
A) the Contract Administrator
Q7: Constructive changes
A) have a positive effect on
Q8: Characteristic of a Critical Path Schedule is
A)
Q9: The Eichleay formula was developed for
A) private
Q10: Sometimes the requirements of proof and detail
Q11: The Owner can grant to an agent
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents