Without a change order clause in the Contract
A) the Owner can do whatever he/she wants
B) the Owner cannot require a change be performed by the Contractor
C) no one gets paid for changes made to the Contract
D) the contract is invalid
Correct Answer:
Verified
Q1: Fortunately, Constructive Acceleration guarantees the Contractor will
Q2: In most cases, the Contract Administrator has
Q4: In most cases, a flaw or ambiguity
Q5: Until one knows otherwise
A) the Contract Administrator
Q6: If a change affects the schedule
A) the
Q7: Constructive changes
A) have a positive effect on
Q8: Characteristic of a Critical Path Schedule is
A)
Q9: The Eichleay formula was developed for
A) private
Q10: Sometimes the requirements of proof and detail
Q11: The Owner can grant to an agent