Solved

A Project Manager Received a Change Request, Immediately Documented the Required

Question 47

Multiple Choice

A project manager received a change request, immediately documented the required changes, and evaluated the impact of and justification for the changes. Which of the following should the project manager do NEXT?


A) Gain approval for the changes.
B) Identify the approval authority.
C) Implement the changes.
D) Create an emergency change request.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents