A vendor is unable to deliver an order by the specified date. Which of the following should be the project manager's NEXT steps? (Choose two.)
A) The project manager should notify the affected project team and, if necessary, adjust the schedule because the project could potentially encounter delays.
B) The project manager should notify the project sponsor to update the schedule in the documentation because the project could potentially encounter delays.
C) The project manager should adjust the schedule in the documentation and, if necessary, take steps to rush other areas of the schedule so the project will not encounter delays.
D) The project manager should update the project management plan in the documentation to reflect the reason for the possible delay in the project timeline.
E) The project manager should update the procurement plan and action items to reflect the possible delay in the project timeline.
Correct Answer:
Verified
Q41: A project manager has contracted a third-party
Q42: Which of the following is a schedule
Q43: Team members have reported that meetings are
Q44: A project manager who is part of
Q45: Due to a new government regulation, a
Q47: A project manager received a change request,
Q48: An authorized change to a construction project
Q49: A project manager needs to track the
Q50: A new project sponsor has joined the
Q51: A project has fallen behind schedule. Upon
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents