Solved

A Scrum Team Works on a Project in 2-Week Sprints

Question 74

Multiple Choice

A Scrum Team works on a project in 2-week Sprints. During the Sprint Planning meeting of the third Sprint, the Product Owner says: "I will be going on holiday in 2 weeks. Let's change the duration of this Sprint to 4 weeks, so that I will be back when it ends." Should the duration of the sprint be increased?


A) Yes, because the Product Owner must be available at the end of a Sprint.
B) Yes, because Sprint duration can be anything between 2 and 4 weeks.
C) No, because the Sprint duration is not based on single events.
D) No, because only Development Team members may change Sprint duration.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents