During the 'lessons learned' meeting at the completion of a project, a project manager should:
A) identify and capture the lessons learned to make sure they are not forgotten.
B) focus on the past - what went wrong and what could have been done better.
C) appropriately apportion blame for aspects of the project that did not meet expectations.
D) invite operational workers, but not invite the project sponsor or key stakeholders.
E) document only the project's failures, and focus on why these occurred.
Correct Answer:
Verified
Q20: If it became clear that a project
Q21: Capitalising on a risk to a project
Q22: Convening a 'lessons learned' meeting with team
Q23: When an activity that is part of
Q24: Team members working on a project will
Q25: During a project's execution phase, what percentage
Q26: Updating expenditure records is an example of
Q27: At a project's completion, a project manager's
Q29: Regular status meetings with the team during
Q30: Along with partial scoping and stakeholders not
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents