Solved

During the 'Lessons Learned' Meeting at the Completion of a Project

Question 28

Multiple Choice

During the 'lessons learned' meeting at the completion of a project, a project manager should:


A) identify and capture the lessons learned to make sure they are not forgotten.
B) focus on the past - what went wrong and what could have been done better.
C) appropriately apportion blame for aspects of the project that did not meet expectations.
D) invite operational workers, but not invite the project sponsor or key stakeholders.
E) document only the project's failures, and focus on why these occurred.

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents