When an activity that is part of a project is not on track, what should a project manager do?
A) Reassign different staff members to the activity
B) Work out what corrective action is necessary to take, and implement it
C) Take over the activity themselves
D) Adjust the project scope downwards and advise stakeholders accordingly
E) None of these responses are correct.
Correct Answer:
Verified
Q18: When stakeholders ask for adjustments to a
Q19: The loss of support for a project
Q20: If it became clear that a project
Q21: Capitalising on a risk to a project
Q22: Convening a 'lessons learned' meeting with team
Q24: Team members working on a project will
Q25: During a project's execution phase, what percentage
Q26: Updating expenditure records is an example of
Q27: At a project's completion, a project manager's
Q28: During the 'lessons learned' meeting at the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents