The WBS is best suited for projects that have a tangible outcome. Which of the following is used when the final outcome of the project is less tangible or is a product of a series of steps or phases?
A) Responsibility matrix
B) Organization breakdown structure
C) A work breakdown structure is still effective for these types of projects.
D) Priority matrix
E) Process breakdown structure
Correct Answer:
Verified
Q44: The integration of the lowest level of
Q45: The highest element in the hierarchical breakdown
Q46: The lowest element in the hierarchical breakdown
Q47: A Process Breakdown Structure can provide a
Q48: One way for a project manager to
Q50: A "Dissemination Mode" is
A) how project schedules
Q51: Having a strong communication plan can go
Q52: A Responsibility Matrix will clarify
A) tasks.
B) supports.
C)
Q53: A communication plan is a key component
Q54: There are 5 steps involved when defining
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents