A project estimator is working on estimates for a project that is very similar to a previous project, in that it has many of the same features and those features have similar costs. Each feature or deliverable will represent the same percentage of the total cost as it did for the previous project. He is using the _________ method of top-down estimating.
A) ratio
B) consensus
C) apportion
D) function point
E) learning curves
Correct Answer:
Verified
Q70: A way to improve estimates on future
Q71: The information necessary to conduct a bottom-up
Q72: The preferred method for situations where the
Q73: The approach to estimating project time and
Q74: Consider a five-mile-long railroad tunnel. Tunnel experts
Q76: The top-down method of estimating project time
Q77: The estimating approach that is best to
Q78: The bottom-up method of estimating where work
Q79: Project costs such as labor and materials
Q80: The top-down method of estimating when the
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents