A(n) ________ constraint addresses the sequence in which project activities must occur even after considering resource constraints.
A) predecessor
B) technical or logic
C) successor
D) serial
E) hard
Correct Answer:
Verified
Q63: If resource demand varies widely over the
Q64: When only one person is responsible for
Q65: Delaying noncritical activities to lower peak demand
Q66: All leveling techniques delay noncritical activities by
Q67: Which constraint category should be considered before
Q69: The shortage of memory chips to produce
Q70: Resource dependency takes priority over the technological
Q71: A shortage of software developers to create
Q72: When scheduling activities in a resource-constrained project,
Q73: In order that the new product is