Which constraint category should be considered before all others?
A) Logical and technical constraints
B) Human resource constraints
C) Material resource constraints
D) Equipment resource constraints
E) Time constraints
Correct Answer:
Verified
Q62: Renovation of a small compartment in a
Q63: If resource demand varies widely over the
Q64: When only one person is responsible for
Q65: Delaying noncritical activities to lower peak demand
Q66: All leveling techniques delay noncritical activities by
Q68: A(n) _ constraint addresses the sequence in
Q69: The shortage of memory chips to produce
Q70: Resource dependency takes priority over the technological
Q71: A shortage of software developers to create
Q72: When scheduling activities in a resource-constrained project,