When a Set of Jobs Must Pass Through Two Workstations

Question 72

Multiple Choice

When a set of jobs must pass through two workstations whose sequence is fixed, ________ is the sequencing rule most commonly applied.


A) critical ratio
B) earliest due date
C) first come, first served
D) slack time remaining
E) Johnson's rule

Correct Answer: