When a set of jobs must pass through two workstations whose sequence is fixed, ________ is the sequencing rule most commonly applied.
A) critical ratio
B) earliest due date
C) first come, first served
D) slack time remaining
E) Johnson's rule
Correct Answer:
Verified
Q67: Sequencing (or dispatching):
A) assigns dates to specific
Q68: Which of the following dispatching rules ordinarily
Q69: Which of the following dispatching rules tends
Q70: Five jobs are waiting to be processed.
Q71: Orders are processed in the sequence in
Q73: Which critical ratio value implies that a
Q74: What is the priority rule that sequences
Q75: Five jobs are waiting for processing through
Q76: Using SPT priority would result in what
Q77: Which of the following is an advantage