Sequencing (or dispatching) :
A) assigns dates to specific jobs or operations steps.
B) assigns jobs to work centers.
C) specifies the order in which jobs should be done at each center.
D) assigns workers to jobs.
E) assigns workers to machines.
Correct Answer:
Verified