Table 7.14
You are responsible for managing a project with the following activities (times are given in weeks) .
-Using Table 7.14, which activity has the largest standard deviation, and how large is that standard deviation?
A) Activity A; 0.83 weeks
B) Activity B; 1.25 weeks
C) Activity D; 1.5 weeks
D) Activity C; 1.25 weeks
Correct Answer:
Verified
Q104: Table 7.3 Q105: In making an estimate of the most Q106: Table 7.2 Q107: Table 7.3 Q108: To calculate the probability of completing a Q110: Table 7.13 Q111: Following are four sets of most optimistic, Q112: Table 7.13 Q113: Table 7.13 Q114: Table 7.14 Unlock this Answer For Free Now! View this answer and more for free by performing one of the following actions Scan the QR code to install the App and get 2 free unlocks Unlock quizzes for free by uploading documents