Table 7.13
All activity times for the project are in weeks.
-Using Table 7.13, what is the critical path of this project?
A) A-D-H
B) C-E-H
C) B-F-G-H
D) C-E-H and B-F-G-H are both critical.
Correct Answer:
Verified