An activity has an optimistic time of 16, a most likely time of 25, and a pessimistic time of 40. What is the expected time for the activity?
A) 15 − 20
B) 20.01 − 25
C) 25.01 − 30
D) 30.01 − 35
E) Over 35
Correct Answer:
Verified