A project has four activities: A, B, C, and D. The amount spent on each activity to date is $22K, $14K, $12K, and $28K respectively. The planned percentages complete for the current date are 90%, 80%, 70%, and 20% respectively. The actual percentages complete for the current date are 100%, 90%, 75%, and 10% respectively. The actual cost of the work performed to date is $40K. What is the BCWS for Activity A?
A) $0 − $5K
B) $5.01K − $10K
C) $10.01K − $15K
D) $15.01K − $20K
E) Over $20K
Correct Answer:
Verified
Q94: A project has four activities: A, B,
Q95: Which of the following takes the least
Q96: A project has four activities: A, B,
Q97: A group of activities combined to be
Q98: The hierarchy of project tasks, subtasks, and
Q100: Which of the following is not an
Q101: A project has four activities: A, B,
Q102: A project has four activities: A, B,
Q103: An activity has an optimistic time of
Q104: A project has four activities: A, B,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents