Question 44

Multiple Choice

A simple project listing of five activities and their respective time estimates are presented here: A simple project listing of five activities and their respective time estimates are presented here:   Using CPM, which activities make up the critical path? A)  A, C, D, E B)  A, B, D, E C)  A, C, B, D, E D)  A, D, E E)  None of these choices are correct Using CPM, which activities make up the critical path?


A) A, C, D, E
B) A, B, D, E
C) A, C, B, D, E
D) A, D, E
E) None of these choices are correct