Solved

What Is a Work Breakdown Structure

Question 47

Multiple Choice

What is a work breakdown structure?


A) A list of the activities making up the higher levels of the project
B) A definition of the hierarchy of project tasks, subtasks, and work packages
C) A depiction of the activities making up a project
D) A Gantt chart
E) A structure that is incompatible with the critical path method

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents