Solved

Table 38 -Using Table 3

Question 90

Multiple Choice

Table 3.8
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 3 B 4 C A,B5 D  A 6 E C4 F D,E2\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 3 \\\text { B } & \cdots & 4 \\\text { C } & A , B & 5 \\\text { D } & \text { A } & 6 \\\text { E } & \mathrm { C } & 4 \\\text { F } & \mathrm { D } , \mathrm { E } & 2 \\\hline\end{array}
-Using Table 3.8,what is the critical path of the above project?


A) B-C-E-F
B) B-C-F
C) A-D-F
D) A-C-E-F

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents