Table 3.8 Activity A B C D E F Immediate Predecessor(s) ⋯⋯A,B A CD,E Time (weeks) 345642 -Using Table 3.8,what is the critical path of the above project?
A) B-C-E-F B) B-C-F C) A-D-F D) A-C-E-F