Table 33 -Using Table 3

Question 87

Multiple Choice

Table 3.3
 Activity  Immediate  Predecessor(s)   Time  (weeks)   A 3 B 3 C 3 D  B 4 E  A,C 4 F  B 4 G  H  E 5 I  E 5\begin{array} { | c | c | c | } \hline \text { Activity } & \begin{array} { c } \text { Immediate } \\\text { Predecessor(s) }\end{array} & \begin{array} { c } \text { Time } \\\text { (weeks) }\end{array} \\\hline \text { A } & \cdots & 3 \\\text { B } & \cdots & 3 \\\text { C } & \cdots & 3 \\\text { D } & \text { B } & 4 \\\text { E } & \text { A,C } & 4 \\\text { F } & \text { B } & 4 \\\text { G } & & \\\text { H } & \text { E } & 5 \\\text { I } & \text { E } & 5 \\\hline\end{array}
-Using Table 3.3,what is the minimum number of activities that would have to be crashed in order to cause a decrease in the project's earliest completion date?


A) 1 activity
B) 2 activities
C) 3 activities
D) 4 or more activities

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Unlock this Answer For Free Now!

View this answer and more for free by performing one of the following actions

qr-code

Scan the QR code to install the App and get 2 free unlocks

upload documents

Unlock quizzes for free by uploading documents