Given the project plan shown below,for each task assume that the best-case duration is 80 percent of the most likely duration,and the worst-case duration is 150 percent of the most likely duration.What is the expected completion time for the critical path?
A) 34 days
B) 21.0 days
C) 35.7 days
D) 22.1 days
Correct Answer:
Verified
Q16: Annie is planning a large surprise party
Q17: A project manager has discovered that three
Q18: In evaluating time-cost trade-offs,we start by crashing
Q19: Given the project data below,what is the
Q20: A project manager has discovered that three
Q22: The four tasks below must be completed
Q23: Given the project plan shown below,which task
Q24: Given the tasks,estimated durations,and crash costs shown
Q25: Task X has a most likely duration
Q26: Given the tasks,estimated durations,and crash costs shown
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents