A project manager has discovered that three tasks are on the critical path for a particular project.She has developed the time estimates (in days) shown in the table below.Complete the table and determine the probability that the project will be completed in 20 days or less.
A) Approximately 92 percent
B) Approximately 88 percent
C) Approximately 75 percent
D) Approximately 84 percent
Correct Answer:
Verified
Q15: Annie is planning a large surprise party
Q16: Annie is planning a large surprise party
Q17: A project manager has discovered that three
Q18: In evaluating time-cost trade-offs,we start by crashing
Q19: Given the project data below,what is the
Q21: Given the project plan shown below,for each
Q22: The four tasks below must be completed
Q23: Given the project plan shown below,which task
Q24: Given the tasks,estimated durations,and crash costs shown
Q25: Task X has a most likely duration
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents