In the project schedule, the duration of the project is
A) equal to or less than the total of the durations for all the individual activities.
B) more than the total of the durations for all the individual activities.
C) always equal to the total of the durations for all the individual activities.
D) always less than the total of the durations for all the individual activities.
Correct Answer:
Verified
Q89: An RFP is the
A) requirements of the
Q90: The baseline plan is set at the
Q91: The Project Management Institute (PMI)is
A) the only
Q92: Which of the following is an example
Q93: The estimated duration of an activity is
Q94: The project management process involves two major
Q95: The project objective must be agreed upon
Q96: Once the project has started, unforeseen circumstances
Q97: Project management is
A) only used on projects
Q98: Constraints for a project are
A) schedule, budget,
Unlock this Answer For Free Now!
View this answer and more for free by performing one of the following actions
Scan the QR code to install the App and get 2 free unlocks
Unlock quizzes for free by uploading documents