Calculate the forecasted cost at completion if the total budgeted cost is $15,000, the cumulative actual cost is $10,000, and the cumulative earned value is $12,000.
A) FCAC = $7,000
B) FCAC = $17,000
C) FCAC = $13,000
D) FCAC = $37,000
Correct Answer:
Verified