The ____ is the sum of the estimated costs of all the specific activities that make up a work package or the project.
A) total budgeted cost (TBC)
B) cumulative budgeted cost (CBC)
C) cumulative actual cost (CAC)
D) cumulative earned value (CEV)
Correct Answer:
Verified
Q38: It may be easier to estimate the
Q39: Facilities costs in the project costs estimate
Q40: The budget for each work package is
A)
Q41: A method for calculating the forecasted cost
Q42: Earned value, the value of _, is
Q44: If the cumulative earned value is $10
Q45: Consider a project that involves painting five
Q46: Calculate the forecasted cost at completion if
Q47: Costs are _ when an item is
Q48: The _ is the amount that was