Which sequencing rule is designed specifically to minimize job lateness?
A) Critical ratio (CR)
B) Earliest due date (EDD)
C) First come,first serve (FCFS)
D) Minimum slack time (MST)
E) Shortest processing time (SPT)
Correct Answer:
Verified