Cost Management: A Strategic Emphasis 5th Edition by David Stout, Edward Blocher, Gary Cokins
Edition 5ISBN: 0073526940
Cost Management: A Strategic Emphasis 5th Edition by David Stout, Edward Blocher, Gary Cokins
Edition 5ISBN: 0073526940Activity-Based Costing, Value-Chain Analysis Hoover Company uses activity-based costing and provides this information:
Manufacturing Activity | Cost Driver | Overhead Rate |
Materials handling | Number of parts | $ 0.45 |
Machinery | Number of machine-hours | 51.00 |
Assembly | Number of parts | 2.85 |
Inspection | Number of finished units | 30.00 |
Hoover has just completed 80 units of a component for a customer. Each unit required 105 parts and 3 machine-hours. The prime cost is $1,200 per finished unit. All other manufacturing costs are classified as manufacturing overhead.
Required
1. Compute the total manufacturing costs and the unit costs of the 80 units just completed using ABC costing.
2. In addition to the manufacturing costs, the firm has determined that the total cost of upstream activities including research and development and product design is $180 per unit. The total cost of downstream activities, such as distribution, marketing, and customer service is $250 per unit. Compute the full product cost per unit, including upstream, manufacturing, and downstream activities. What are the strategic implications of this new cost result?
3. Explain to Hoover Company the usefulness of calculating the total value-chain cost and of knowing costs of different value-creating activities.
Step 1 of 4
Activity based costing method which is commonly known as ABC method, is a costing method where indirect cost is assigned to product on the basis of activities identified, used in producing the product.
Step 2 of 4
Step 3 of 4
Step 4 of 4
Why don’t you like this exercise?
Other